Weekly Status Report for
Benchmark Database Project
Dev
Lead:
Week
Ending:
{mosgoogle}
Project
Schedule Summary:
|
|
Dur
|
Baseline
|
Last Week
|
This Week
|
% Comp
|
|
Project
Start Date
|
N/A
|
01/01/1998
|
10/27/1998
|
10/27/1998
|
100%
|
|
Project
Est/Actl M1 Architecture Finish Date
|
43 d
|
01/21/1999
|
12/29/1998
|
12/29/1998
|
100%
|
|
Project
Est/Actl M2 GUI Tools Finish Date
|
13 d
|
|
01/29/1999
|
01/29/1999
|
100%
|
|
CO1: Break in Project to Assist Other Project
|
8 d
|
|
-1.5 weeks
|
-1.5 weeks
|
100%
|
|
Project
Est/Actl M3 Static Internet Reports Finish Date
|
7 d
|
|
02/26/1999
|
02/26/1999
|
100%
|
CO2: Break in Project to Assist
Other Project
|
10 d
|
|
-2 weeks
|
-2 weeks
|
100%
|
|
Project
Est/Actl Testing 1 Finish Date
|
5 d
|
02/03/1999
|
04/13/1999
|
04/13/1999
|
100%
|
|
CO3: Break in Project for DAT
|
40 d
|
|
- 8 weeks
|
- 8 weeks
|
100%
|
|
Project
Est/Actl Testing 2 Finish Date
|
20 d
|
|
06/04/1999
|
06/11/1999
|
85%
|
|
Project
Est/Actl M4 Production Environment Setup FDt
|
45 d
|
|
06/09/1999
|
06/09/1999
|
100%
|
|
Project
Est/Actl M5 Production Run Finish Date
|
4 d
|
|
06/15/1999
|
06/17/1999
|
10%
|
|
|
|
|
|
|
|
|
Scope,
# Days
|
|
67.5 days
|
162
days
|
164 days
|
|
|
Scope,
# Tasks
|
|
109
|
109
|
109
|
|
{mosgoogle}
Acceptance
Criteria / Testing:
|
Measure
|
Number
|
Percent
|
|
Total
Acceptance Criteria
|
316
|
100%
|
|
Pass
|
246
|
78%
|
|
Fail
|
10
|
3%
|
|
Untested
|
49
|
16%
|
|
Removed
|
11
|
3%
|
Bug
Metrics:
Status |
Highest
|
Medium
|
Low
|
Lowest
|
Not
Assigned
|
Total
|
|
Closed
|
9
|
31
|
28
|
2
|
3
|
73
|
|
Open
|
0
|
0
|
0
|
0
|
1
|
1
|
|
Resolved
|
1
|
8
|
8
|
0
|
3
|
20
|
Issues:
1. Assisted other
projects for a grand total of 11.5 weeks!!! Thats almost 3 months! Now add
in Market View for several more weeks.
2. Testing is
almost complete. Uncovered lots of good
bugs. A few more to fix and re-test.
3. Will not
performance test this quarter due to time constraints.
Tasks
Completed This Week
· Re-worked schedule. Re-organized bug list. Debugging
& unit testing. Workload on this
project is light for me.
· SQL Server Upgrade / Production Environment Setup
Tasks
Planned For Next Week and Beyond
· Don to finish with Acceptance Criteria testing.
· Matt to finish debugging.
· Any time to run production environment stress and
performance testing? May need to defer.